Buying, Selling & Installing Built-in Toilets in Ho Chi Minh City

  • 18/01/2023
  • The product " assembled toilet " is designed and built by Hoang Sa Viet Company with a variety of models, functions and locations. The built-in toilet is an extremely optimal and effective construction method. Most recently, Hoang Sa Viet has successfully installed the " Building Toilet Project at Bach Dang Wharf, HCMC ". If you are interested in this new model, you can refer to our actual project to better understand this type.

    GENERAL INFORMATION OF THE INSTALLATION TOILET PROJECT IN HCMC

    • Category: Built-in toilets

    • Location: (Bach Dang Wharf) 27 Ton Duc Thang, Ben Nghe, District 1, HCMC

    • Construction & design unit: Hoang Sa Viet Construction

    • Scale of area: 18m2 (1 frame 3x6)

    • Completion time: 4 days

    • Warranty: 10 years

    Built-in Toilets In Ho Chi Minh City
    Built-in Toilets In Ho Chi Minh City

    COMBINED TOOLS IN HCMC

    Integrated toilet (assembled toilet) is a type of public toilet located at Bach Dang Wharf, Ho Chi Minh City. This model is built from a basic prefab frame, different from the reinforced concrete public toilets we often see. Public toilets built in this fashion have shortened construction time, saved construction costs, are safe, secure and highly aesthetic.

    PROCESS OF CONSTRUCTION OF INSTALLATION TOOLS IN HCMC

    To complete the assembled toilet project in Ho Chi Minh City, there are the following stages:

    Stage 1: Design drawings

    Hoang Sa Viet will rely on the construction requirements of the investor and the information provided such as dimensions, characteristics to come up with the most suitable ideas and drawings. After that, we will continue to complete the finished drawing.

    Stage 2: Carrying out construction and installation

    After having a full plan as well as detailed drawings, the technical staff of Hoang Sa Viet will carry out the installation at the required location. With an area of ​​​​18m2, it only takes 3 days to complete from the inside out.

    Stage 3: Equipment installation

    After completing the assembly of the prefab toilet frame, Hoang Sa Viet will proceed to install the required equipment and the plumbing and electrical systems will be carefully constructed.

    Stage 4: Handover and acceptance of the project

    At this stage, the investor will check all equipment and systems and Hoang Sa Viet will make final edits to hand over.

    Technical staff is completing the assembled toilet in Ho Chi Minh City
    The technical staff is in the process of completing the assembled toilet in Ho Chi Minh City

    CONSTRUCTION OF COMBINED TOILET IN HCMC

    Overview of pre-assembled toilets in Ho Chi Minh City, made from a basic prefabricated frame of 18m2 with a length of 3m and a width of 6m. Used as a public toilet, there are 6 separate toilets separated from each other by a 3-layer panel. The equipment is fully equipped by us upon request, especially the septic tank is installed with large capacity, high quality for waste treatment. The floor is made of simili-lined cemboard, which is safe, sturdy and anti-slip.

    DETAILED PICTURE OF THE HO CHI MINH CITY PROJECT

    The internal structure of the assembled toilet in Ho Chi Minh City
    The internal structure of the assembled toilet in Ho Chi Minh City
    The internal structure of the assembled toilet in Ho Chi Minh City
    The internal structure of the assembled toilet in Ho Chi Minh City
    The internal structure of the assembled toilet in Ho Chi Minh City
    The internal structure of the assembled toilet in Ho Chi Minh City

    CONCLUSION: The above article is the detailed information of the actual project "Assembled toilet in HCMC". If you are looking for more information, you can contact us for the most specific advice.